SOTA Product Development Plan (2026-08)

This plan turns “best LiDAR SLAM OSS” into measurable engineering work. A SOTA claim is always limited to a named dataset, metric, revision, and execution condition. The project must not publish a blanket “best overall” claim.

Phase 0: Current Baseline

Area Current evidence Honest status Next proof needed
HILTI exp04 accuracy lidarslam_ros2 0.0565 m median APE vs GLIM CPU 0.0866 m Measured win in the existing three-run snapshot Re-run once after the next frozen release candidate
HILTI exp04 runtime RTF 0.993 vs GLIM CPU 0.244 GLIM wins Profile the frontend/backend boundary and remove the largest bottleneck
HILTI exp04 memory 586.83 MB vs GLIM CPU 690.88 MB maximum peak RSS Measured win in the existing snapshot Preserve under the same-input release candidate
Multi-dataset research candidate Voxel-SLAM v17 geomean APE 2.2836 m vs GLIM 5.0779 m Promising, but not the default and not fresh-blind Graduate only after default-path and holdout gates pass
FAST-LIVO2 comparison Historical exp04 ROS1/paced snapshot scores 0.05298 m median APE, about 4.7 GiB RSS, and about 135 s mapper wall time FAST is the current accuracy target, but the old pacing/input/runtime contract is not comparable to the current unpaced harness Complete one bounded, same-input current-contract run
Reproducibility Frozen profiles, hashes, reports, and fail-closed publication tooling exist Strong infrastructure, incomplete current rival evidence Produce a compact release evidence bundle
Extensibility Versioned registration plugin API, clean consumer/template, optional FAST/Small adapters, and transactional loader exist Humble/Jazzy absent/present builds and targeted runtime rollback gates pass Add the matrix to CI and broaden real-bag plugin characterization
First use Docker demo is one command; source demo is two commands Good start, fragmented diagnostics One doctor and one source first-map entrypoint
Continued use Run diagnosis and map verification exist Useful tools, fragmented workflow Saved run manifest, resume, support bundle, migration guide

The numbers above describe existing evidence, not a new 2026-08 measurement. See Comparison for revisions, limitations, and reproduction details.

2026-08-28 registration dependency checkpoint

The campaign at /media/user/aiueo1/benchmarks/registration-plugin-dependency-capture-20260828-decoded-bound-v8 completed Humble/Jazzy × dependency absent/present exactly once per row. All four rows completed 19 phases with PASS_REVIEW_REQUIRED; the aggregate has zero partial rows. This proves dependency capture only; it is not a runtime or performance result.

The follow-up compatibility work passed all four intended legs: clean external consumer plus author-template builds on Humble and Jazzy with optional dependencies absent, and real small_gicp plus fast_gicp adapter builds and direct-fixture tests on both distros with the dependencies present. The helper CMake module is now exported by lidarslam_plugin_interfaces, so an external plugin no longer reaches back into this repository's source tree. Humble also exposed a portable-test bug: PointXYZI padding was being compared as if it were public point data; the test now compares the four public float fields bit-for-bit.

The actual DSO gate loads the built plugin, validates its contract, runs a load session, and reports no host/plugin ODR collision. Targeted loader tests also pass constructor rejection, activation rejection with lease preservation, and post-commit rollback; scanmatcher resource failure restores the prior external candidate, and backend preflight rejection remains fail-closed. These are runtime compatibility results, not SLAM accuracy or performance claims.

2026-08-28 development checkpoint (n=1)

Two distinct configurations were each run once on the current dirty development tree. The product-default profile completed in 79.94 s (RTF 0.635), used 606,760 KiB peak RSS, and scored 0.07156 m APE RMSE over all seven control points. The competitive-v2 profile completed in 54.80 s (RTF 0.436), used 591,372 KiB peak RSS, scored 0.06802 m over all seven control points, and produced a verified Autoware map with 1,735,059 points across 32 tiles.

On the exact six-point common reference used by the existing GLIM snapshot, competitive-v2 scores 0.04712 m versus GLIM's 0.08662 m three-run median. Its 577.51 MiB peak RSS is also below GLIM's 674.15 MiB median, but its 54.80 s wall time remains above GLIM's 30.66 s median.

This is a development signal, not README claim evidence: the worktree and rival source closure were not sealed and ours has only one measurement. It shows the immediate priorities clearly: preserve the observed accuracy and memory advantage, then reduce competitive-v2 wall time by at least 1.79x to beat the GLIM median. RKO-LIO took 47.51 s of the run; its 1,256 ICP calls averaged 21.60 ms, making frontend ICP the next measured bottleneck. The run also exposed and fixed three harness blockers: ROS 2 launch argument construction, leaked ThreadSanitizer instrumentation, and ordinary-run completion being misclassified as M6A10 evidence failure. Sparse graph anchors are now retained as traj_corrected_sparse.tum, while traj_corrected.tum receives full-rate correction propagation before scoring.

The historical FAST-LIVO2 exp04 snapshot is a separate directional constraint, not a fair current comparison. Its three-run all-seven-point APE median is 0.05298 m, so competitive-v2 would need roughly a 22% reduction from 0.06802 m to beat it on this metric. That snapshot used a ROS1-converted bag and paced playback, consumed about 4.7 GiB peak mapper RSS, and took about 135 s mapper wall time. The next FAST run must use the current same-input, unpaced online- compute and memory contracts before any cross-system claim; the old result is nevertheless sufficient to prevent treating the GLIM-only win as overall SOTA.

A later quiescent development run on the same day validated the task-local correspondence reduction: the authoritative 1,258-pose RKO trajectory is byte-identical to the pre-change dump (3ffde307...), while mean ICP time moved from 21.60 ms to 20.92 ms and RKO-LIO wall time moved from 47.51 s to 46.55 s. The full pipeline completed in 52.74 s (RTF 0.419), used 599,800 KiB peak RSS, and passed all eight Autoware map checks. Because this is n=1, the timing and RSS deltas are directional rather than statistical claims; numerical identity and removal of the shared hot-path atomic are the adoption grounds.

The optimized piecewise-gyro candidate also completed its single predeclared development run. Scan-local prefix SO(3) integration reduced deskew from the historical 62.32 ms to 8.89 ms per scan. The pipeline completed in 50.40 s (RTF 0.401), used 593,292 KiB peak RSS, passed all eight map checks, and scored 0.05057 m interpolated APE over all seven checkpoints. That clears the 0.05307 m all-seven accuracy target and is directionally below the historical FAST-LIVO2 median, but it scores 0.04745 m on the six-point common subset versus the frozen competitive-v2 value of 0.04675 m (a 1.48% regression). The candidate therefore remains ungraduated under its predeclared no-regression gate. No README claim is authorized from these dirty-tree, single-run results.

Measurement Policy

  • Normal development and OSS comparison uses one complete run per fixed condition (n=1).
  • Repeat only when the run is anomalous, a regression must be isolated, or a release/publication result needs confirmation. Every table states its actual n; an n=1 result is never presented as statistical evidence.
  • Same-input comparisons freeze dataset hash, calibration, revision, build type, host, CPU/thread limits, warm-up policy, scorer, and completion rule.
  • Failed and incomplete runs remain visible. A result is publishable only when all required artifacts and identities pass the publication gate.
  • “SOTA” means a win on a named metric and benchmark. “Overall SOTA” is not a release label unless all predeclared accuracy, completion, runtime, memory, map-quality, and reproducibility gates pass.

Priorities And Capacity

Use the following planning budget per milestone:

  • 60% core SLAM accuracy, completion, runtime, and map quality.
  • 25% first-use and continued-use product quality.
  • 15% benchmark/release infrastructure.

Infrastructure work is pulled forward only when it blocks the next bounded SLAM run, user workflow, or release decision.

Delivery Phases

Phase 1: First Useful Map

Target: a new user reaches a verified map in at most three commands, with a median clone-to-first-map time of 15 minutes or less on a documented machine.

  • Provide a read-only environment doctor with actionable fixes.
  • Provide one source first-map command while retaining the one-command Docker path.
  • Make missing ROS setup, tools, submodules, disk space, dataset, and output failures point to the exact next command.
  • Test Humble/22.04 and Jazzy/24.04 clean environments.
  • Record local, opt-in timing only; do not add network telemetry.

Exit gate: at least 90% of clean supported-environment trials produce a verified map, and all failures leave an actionable diagnostic.

Implementation checkpoint: lidarslam_doctor.py and run_first_map.sh now provide the unified diagnostic and first-map entrypoints. Clean Humble/Jazzy trial evidence remains before this phase can pass its exit gate.

Phase 2: Fair OSS Baseline

Freeze ours, GLIM, and FAST-LIVO2 revisions and run each condition once. Start with HILTI exp04, then one MID-360 sequence and one fresh holdout. Capture APE, completion, RTF, peak RSS, map-quality metrics, configuration, host identity, and all failures in the same report.

Exit gate: a reviewer can reproduce the table from published commands and artifacts, and the README generator refuses unsupported prose.

Phase 3: Core SLAM Iteration

Profile before changing algorithms. Improve the largest observed bottleneck, then run the fixed condition once. Candidate areas are frontend registration, keyframe/submap policy, loop candidate ranking and verification, optimizer scheduling, memory ownership, and deterministic offline I/O.

Exit gate: aggregate accuracy improves by at least 10% against the best pinned rival without a completion, real-time, memory, or map-quality regression. If it does not, document the rejected candidate and select the next bottleneck.

Runtime iteration log

  • 2026-08-28 / icp-task-local-correspondence-count: replace the shared per-correspondence atomic increment in RKO-LIO's deterministic TBB reduction with a task-local integer reduced alongside H/b/chi. The Release build and all RKO-LIO tests pass. A full exp04 execution under severe unrelated CPU load produced an authoritative 1,258-pose frontend dump byte-identical to the pre-change dump (3ffde307...), proving numerical equivalence for that sequence. A later quiescent n=1 run preserved that exact dump, reduced mean ICP time from 21.60 ms to 20.92 ms, and completed RKO-LIO in 46.55 s. Adopt the simpler task-local reduction; do not present the one-run timing delta as a release performance claim.
  • The same interference exposed a benchmark observation flaw: the ROS topic logger missed startup poses even though the offline node's atomic dump was complete. The benchmark now requires exactly one authoritative full-rate dump and uses it for scoring in every map-save mode.
  • 2026-08-28 / competitive-piecewise-v1: historical piecewise-gyro and fixed-lag candidates scored 0.052948 m and 0.052914 m respectively on all seven exp04 points, at non-realtime RTF 1.36--1.79. The current competitive- v2 raw and graph-corrected paths are position-identical (no accepted loop edges), so the FAST accuracy gap is frontend-only. A bounded candidate now adds only piecewise_gyro_deskew=true to competitive-v2, retaining its 50-iteration budget, 2.25 keypoint-voxel multiplier, convergence threshold, and publisher queue. One quiescent run must beat or match 0.05307 m, remain RTF <= 1, preserve memory/map gates, and avoid regression on the six-point common subset before adoption.
  • 2026-08-28 / competitive-piecewise-v1 result: the optimized prefix integrator clears the all-seven, realtime, memory, and map gates at 0.05057 m interpolated APE, RTF 0.401, 593,292 KiB, and 8/8 map checks. It misses the strict common-six no-regression gate by 1.48% (0.04745 m versus 0.04675 m), so keep it as a research profile rather than graduating it. The next candidate must use a sensor/uncertainty-derived decision fixed before evaluation; it must not branch on exp04 time, checkpoint identity, or post-hoc GT tuning.
  • next / uncertainty-gated-zoh-v1 preregistration: compare the mean-rate and prefix-integrated rotations at IMU boundaries and use a covariance-normalized discrepancy to select/blend them. Differences within a fixed three-sigma bound return the existing mean model directly; high-SNR within-scan angular motion may move continuously toward the piecewise result. Non-finite input, timestamp reversal, insufficient IMU coverage, or an abnormal sample gap fails closed to the mean model. The decision must use sensor calibration or a deterministic GT-blind static-initialization noise estimate, and record its mode, calibration/noise identity, decision counts, and fallback reasons. HILTI's checked-in calibration contains gyro bias but no noise density or clock-offset uncertainty, so no guessed constants are authorized. Before any run, freeze the estimator and require common-six APE <= 0.046755 m, all-seven APE <= 0.05307 m, 1,258 poses, RTF <= 1, memory acceptance, and all map checks. Apply the same rule without per-sequence thresholds to exp01, exp04, exp07, and the fresh holdout.

Phase 4: Continued Use

  • Save an immutable run manifest containing effective config, revisions, input identity, output inventory, and metrics.
  • Resume interrupted offline sessions without silently mixing configurations.
  • Export a privacy-safe diagnostic bundle with logs and redacted environment facts.
  • Publish compatibility and config-migration notes for every stable release.
  • Maintain task recipes for Autoware mapping, MID-360 field capture, large loops, GNSS georeferencing, and coloured maps.

Exit gate: an operator can reproduce, resume, diagnose, and migrate a mapping job without reconstructing undocumented shell history.

Implementation checkpoint: schema-v2 portable run manifests now hash every rosbag metadata/storage byte and bind the ordered records into a deterministic input tree identity. A read-only verifier reopens that identity together with the effective configs, revision/tracked binary-diff identity, and output file hashes without a large-file size-only exception; a redacted support-bundle exporter is also present. The public map runner rejects non-empty output directories instead of silently mixing prior artifacts. Identity-bound checkpoint/resume semantics and release migration notes remain open.

Phase 5: Evidence And Release

Publish only generated, qualified claims. Each row includes revision, input hash, host/limits, scorer, measurement count, completion, APE, RTF, RSS, and map quality. The release checklist verifies docs, source builds, supported distro matrix, plugin consumer compatibility, and evidence bundle hashes.

Phase 6: Extensible OSS Platform

Complete the versioned frontend/backend plugin contracts, lifecycle and thread-safety rules, capability discovery, ABI/API compatibility policy, out-of-tree consumer SDK, minimal plugin template, conformance tests, and fail-closed fallback behavior. Keep the default installation small; advanced algorithms remain optional plugins.

Phase 7: Long-Term Differentiation

Long-term SLAM is the primary future differentiator: persistent map identity, multi-session localization and merging, change detection, map aging, dynamic object memory, bounded storage, and safe rollback. Application differentiation includes fleet map maintenance, construction progress/change reports, warehouse digital twins, disaster inspection, vegetation/infrastructure monitoring, and privacy-preserving on-premise map updates.

These items are intentionally scheduled after the default single-session path and evidence pipeline are reliable. Architecture boundaries and staged gates are detailed in Extensible OSS Architecture.

Milestone Scorecard

Milestone Product metric SLAM/evidence metric
M1 First map ≤3 commands, p50 ≤15 min verified Autoware bundle
M2 Repeat use saved manifest + resume + diagnostic bundle byte-identifiable inputs/config/outputs
M3 Competitive one run per fixed condition complete APE/RTF/RSS/map-quality table
M4 Release supported clean-env success ≥90% all publication and regression gates pass
M5 Platform external plugin builds on Humble/Jazzy no silent fallback; conformance suite passes
M6 Long term repeatable multi-session workflow change/aging/rollback metrics pass